Item Coversheet


CITY OF KYLE, TEXAS

Task Order No. 9 - Rehabilitation of Dacy Lane Elevated Tank and Ground Storage Tank No. 2 at Yarrington Road

Meeting Date: 6/20/2017
Date time:
7:00 PM

Subject/Recommendation:

Approve contract Task Order No. 9 to NEPTUNE-WILKINSON ASSOCIATES, INC., Austin, Texas, in an amount not to exceed $32,000.00 for the purpose of providing engineering and inspection services for rehabilitation of the Dacy Lane Elevated Tank (300,000 gallons) and ground storage tank No. 2 at Yarrington Road (500,000 gallons). ~ Leon Barba, P.E., City Engineer

Other Information:

Maintenance is required on the Dacy Lane Elevated Storage Tank (300,000 gallons).  The exterior paint system is in poor to fair condition, there is moderate internal biofilm buildup on wall plates, a light sediment layer needs to be removed from the floor and some safety improvements are needed.

 

The 500,000 gallon ground storage tank (No. 2) at Yarrington Road has minor interior staining at the water line, minor corrosion on the interior side of the plates, a light sediment layer needs to be removed and some safety improvements are needed.

 

The plan is to complete the rehabilitation of the Dacy Lane Elevated Storage by the end of the 2017 calendar year and the Yarrington Road No. 2 tank in early 2018.


Legal Notes:

N/A

Budget Information:

A Fiscal Note is attached.



ATTACHMENTS:
Description
NWA Proposal - Task Order No. 9
Fiscal Note