Yarrington and FM 1626 Tanks Rehabilitation Change Order No. 1

Meeting Date: 4/18/2017
Date time:
7:00 PM

Subject/Recommendation:

Approve Change Order No. 1 to TRI-STATE COATINGS, Wadena, MN, in an amount of $43,400.00 for a total contract amount not to exceed $222,900.00 for additional work on the Yarrington and FM 1626 Tanks Rehabilitation  Project. ~ Leon Barba, P.E., City Engineer 

Other Information:

Three items are being added to the existing contract with Tri-State Coatings. 

 

1.) The downtown elevated tank will be repainted with the same color scheme along with replacing the logo to both sides.  Along with repairs to the interior coating of the tank, a safety climb cable will also be installed on the exterior ladder.   This cost is $40,000.00.

 

2.) An additional logo was added on the FM 1626 Tank at a cost of $3,000.00.

 

3.) Seal gap between tank bottom plate and concrete ring foundation at a cost of $400.00.


Legal Notes:

N/A

Budget Information:

A Fiscal Note is attached.