Item Coversheet


CITY OF KYLE, TEXAS

Amendment No. 1, Elliott Branch WW Interceptor Project Phase 1

Meeting Date: 5/21/2019
Date time:
7:00 PM

Subject/Recommendation:

Approve Amendment No. 1 to the contract with ESPEY CONSULTANTS, INC., dba RPS, Austin, Texas, in the amount of $592,263.00 increasing the total contract amount not to exceed $865,520.00 for providing project management, data collection and investigations, preliminary and final engineering, permitting, and bid services for the Elliott Branch Phase 1 Wastewater Interceptor Project. ~ Leon Barba, P.E., City Engineer


Other Information:

The scope of work included in this amendment includes:

 

  • Design approximately 1,130 feet of 8” wastewater line
  • Design approximately 1,830 feet of 12” wastewater line
  • Design approximately 7,400 feet of 12” reclaimed waterline
  • Design approximately 1,850 feet of 8” waterline
  • Design approximately 1,600 feet of 12” waterline
  • Design approximately 1,150 feet of roadway and ditch reconstruction
  • Extended design timeline and associated project management, subconsultant coordination, and contract administration activities
  • Budget adjustments for regulatory changes and updated rates due to the extended hold the project encountered

 

See attached Exhibit A for a full description of Amendment 1. 

 

Legal Notes:

N/A

Budget Information:

A Fiscal Note is attached.