CITY OF KYLE, TEXAS
Amendment No. 1, Elliott Branch WW Interceptor Project Phase 1
|
Meeting Date: 5/21/2019
Date time:7:00 PM |
| | | |
| | | | | | | |
Subject/Recommendation: |
Approve Amendment No. 1 to the contract with ESPEY CONSULTANTS, INC., dba RPS, Austin, Texas, in the amount of $592,263.00 increasing the total contract amount not to exceed $865,520.00 for providing project management, data collection and investigations, preliminary and final engineering, permitting, and bid services for the Elliott Branch Phase 1 Wastewater Interceptor Project. ~ Leon Barba, P.E., City Engineer |
Other Information: |
The scope of work included in this amendment includes:
- Design approximately 1,130 feet of 8” wastewater line
- Design approximately 1,830 feet of 12” wastewater line
- Design approximately 7,400 feet of 12” reclaimed waterline
- Design approximately 1,850 feet of 8” waterline
- Design approximately 1,600 feet of 12” waterline
- Design approximately 1,150 feet of roadway and ditch reconstruction
- Extended design timeline and associated project management, subconsultant coordination, and contract administration activities
- Budget adjustments for regulatory changes and updated rates due to the extended hold the project encountered
See attached Exhibit A for a full description of Amendment 1.
|
Legal Notes:
| N/A |
Budget Information:
|
A Fiscal Note is attached.
|
| | | |
|