A final walkthrough was completed on December 19, 2016. The punch list items have been completed on the project. The street, drainage, water and wastewater improvements have been constructed in substantial accordance with the City's requirements. Record drawings have been provided to the City.
A Maintenance Bond (The Hanover Insurance Company - Bond No. 1048932) has been provided for a period of two years in the amount of $149,616.21.
|