Tenorio Addition Wastewater System Rehabilitation Project - Change Order No. 1 Guerra Underground

Meeting Date: 1/17/2017
Date time:
7:00 PM

Subject/Recommendation:

Approve Change Order No. 1 to GUERRA UNDERGROUND, LLC, Austin, Texas, for the Tenorio Addition Wastewater System Rehabilitation Project, Phase One B in an amount not to exceed $35,803.36 for a total contract amount not to exceed $479,743.36 for additional labor and equipment caused by a restriction of work hours due to school related traffic. ~ Leon Barba, P.E., City Engineer

Other Information:

This project had work restrictions from 9am to 3pm for a 50 foot section on Center St. in the bid documents.  This was established in order to minimize the impact to the school buses and parents dropping and picking up children at Wallace Middle School based on an aggressive work schedule.  However, the construction continued in the area and a decision was made to extend the restricted work hours in order to maintain uninterrupted traffic flow through the area adjacent to the school during the morning and in the afternoon. 

Legal Notes:

N/A

Budget Information:

A Fiscal Note is attached.